Chemise Road Repair/Surfacing

Chemise Road Repair/Surfacing

PROJECT INFORMATION

COMMUNITY LIAISON

Munselle Civil Engineering, Inc. ? Cort Munselle at (707) 395-0968
chemise@munsellecivil.com


CONTRUCTION HOURS

Limited weekdays, 7:00am to 5pm
Delays or closures limited to 8am to 5pm


PRELIMINARY CONSTRUCTION SCHEDULE

Thursday May 7 - Friday May 8
Mobilize equipment, no delays other than big trucks using road, passing issues

May 11-15 , 18-22
Road Grading, drainage swales, guard rail installation (0 to 15 minute delays)

May 25-29, June 1-5
Grade Road, Install Base Rock, Install Subdrain, Install Rock riprap in ditch (20 to 30 minute delays)

June 8-12
Chip seal upper road (60 min. delays)

BREAK IN CONSTRUCTION

June 23 (Tuesday)
Fine grade rock for paving (20 to 30 minute delays)

June 24-26 (Tuesday through Friday)
Paving - ROAD CLOSED 8am-5pm (Possibly longer on hot days ? latest 8pm)

June 29 - July 3rd
Chis Seal Maintenance (30 minute delays)

BREAK IN CONSTRUCITON

August and/or September
A/C Berm (1 day)
Additional chip seal layer over asphalt to provide more grip in cold conditions (1day)
Evaluate speed bumps, additiona signage, etc.

Construction schedule is subject to change