PROJECT INFORMATION
COMMUNITY LIAISON
Munselle Civil Engineering, Inc. ? Cort Munselle at (707) 395-0968
chemise@munsellecivil.com
CONTRUCTION HOURS
Limited weekdays, 7:00am to 5pm
Delays or closures limited to 8am to 5pm
PRELIMINARY CONSTRUCTION SCHEDULE
Thursday May 7 - Friday May 8
Mobilize equipment, no delays other than big trucks using road, passing issues
May 11-15 , 18-22
Road Grading, drainage swales, guard rail installation (0 to 15 minute delays)
May 25-29, June 1-5
Grade Road, Install Base Rock, Install Subdrain, Install Rock riprap in ditch (20 to 30 minute delays)
June 8-12
Chip seal upper road (60 min. delays)
BREAK IN CONSTRUCTION
June 23 (Tuesday)
Fine grade rock for paving (20 to 30 minute delays)
June 24-26 (Tuesday through Friday)
Paving - ROAD CLOSED 8am-5pm (Possibly longer on hot days ? latest 8pm)
June 29 - July 3rd
Chis Seal Maintenance (30 minute delays)
BREAK IN CONSTRUCITON
August and/or September
A/C Berm (1 day)
Additional chip seal layer over asphalt to provide more grip in cold conditions (1day)
Evaluate speed bumps, additiona signage, etc.
Construction schedule is subject to change